The Graham/Fishcreek Intersection Improvement Project signal work began May 8, 2023, shortly after the signal poles arrived. All the underground signal work was completed by June 1, 2023, the original scheduled delivery date for the signal equipment. However, not all the signal equipment has been delivered and final signal installation will begin immediately upon arrival.
Future construction over the summer months includes removing the traffic islands, implementing access management, improving commercial driveways, reconstructing signals, upgrading pedestrian amenities, new sidewalks, resurfacing and new pavement markings.
The project was awarded last August to Shelly and Sands, Inc. and signal items were ordered last fall. The project is to be completed by the end of summer. This project was needed for highway safety and the signals were over thirty years old. All equipment needed updated.
If you have any questions, please contact the Engineering Department at 330-689-2719 or jmccleary@stow.oh.us.
James D. McCleary, P.E., P.S.
City Engineer